OBJECTIVE

There are several phases in getting a large commercial aircraft through production and delivered to an airline. After roll-out from the factory, assembly work is completed on the flight line, final ground tests are completed, and test flights are conducted by both manufacturer and airline test pilots, culminating in airplane delivery to the airline for entry into revenue service.

 

Unfortunately for the manufacturer, this isn’t always a smooth process. In-flight anomalies and failures known as “squawks” can occur during test flights and must be remedied. This is an arduous and expensive process, requiring sign-off by the manufacturer’s Engineering, Quality and Operations teams, followed by acceptance by the airline customer and their flight crew. For significant issues or problems without a known and proven fix, additional test flights may be required to demonstrate that the problem was resolved. This sometimes results in recurring issues that require numerous test flights, which are extremely costly – significantly cutting into per-aircraft profit margins.

 

CHALLENGES

Belcan Engineers formed the core of a Flight Improvement Team tasked with identifying and resolving chronic flight squawks. As the improvement effort evolved, the role of the team expanded to identify issues occurring during pre-flight testing, allowing the team to implement creative solutions to resolve issues in order to reduce re-work and to minimize flight schedule delays.

 

Using a systems engineering methodology, Belcan determined which problems were causing the largest disruptions to production flight-testing. The manufacturer’s Quality Management System used by the Quality and Operations teams failed to flag recurring issues so the Flight Improvement Team created and populated a flight squawk database by reviewing and categorizing every squawk reported by the flight crews. This list was then prioritized based on the rate of occurrence per failure, and its impact to the flight profile. This systematic approach resulted in a comprehensive, prioritized list of chronic issues. Using this priority ranking, the team then worked to determine the root cause of the failures, and devised a short-term containment strategy to reduce impact to future flights as well as pursuing a final resolution to the issue.

 

To devise final resolutions to squawks, Belcan investigated each chronic issue in order to identify the underlying cause for these repeated failures. While the specific root causes were different, Belcan frequently identified patterns that fell into broad categories, such as manufacturer quality, supplier quality, and engineering design errors and inadequacies.

 

Belcan worked with Industrial and Manufacturing Engineering teams to get airplane assembly drawings updated and corrected, and to get functional tests clarified or rewritten to better catch chronic issues. Belcan also worked with the Quality and Operations teams to identify areas where retraining was required to ensure compliance with released engineering.

 

Belcan worked with both the manufacturer’s Supplier Management and Design Engineering teams and directly with the supplier’s Engineering and Operations teams to identify and resolve recurring issues that were occurring at the Supplier’s manufacturing site. Belcan involved the manufacturer’s Supplier Quality representatives to ensure supplier audits were performed as required. In some cases, the manufacturer’s production experts, both engineers and seasoned factory mechanics, were brought in to help suppliers optimize their production process.

 

SOLUTION

Belcan worked with the Design Engineering community to identify errors in design that were resulting in failures. These issues included; inconsistent released engineering; inadequate analysis of tolerance stack-ups that resulted in failures when products that were within the allowed tolerance stack were unable to meet the system’s higher level requirement; and failure to account for environmental effects, usually temperature and pressure, causing failures in flight on systems that tested “good” on the ground.

 

Depending on the scope of investigation required, the identified corrective action, and the certification requirements, there can be a significant delay between problem identification and final resolution implementation on flight line airplanes. One of the most crucial tasks of the Flight Improvement Team was to identify containment approaches to shield the flight line from continuing failures while waiting for the resolution to be implemented. A common method to provide this protection was to institute new ground tests, or rewrite existing tests, to capture the specific failures while the corrective action was in process. Additional tests increased the labor burden in the factory and on the field, so this action needed to be carefully weighed against the likelihood the added testing would screen out the problem. Ideally, improved supplier acceptance tests would be immediately implemented to reduce the amount of time that these tests would have to be performed on the assembled aircraft as they moved down the assembly line and into flight test. Belcan worked closely with the responsible engineers in design, test, and at the supplier, to devise potential screening measures for implementation up the value chain as quickly as possible.

 

OUTCOME

Belcan Engineering consultants were able to work across organizational silos to bring a multi-functional team approach to identifying and resolving flight issues.

 

For the engineering communities, Belcan was able to communicate with the design teams directly and inform them of failures of their systems, and then work with Engineering leadership to ensure that the resolution of these failures was properly prioritized.

 

Belcan was also able to bring together the Quality, Operations, and Supplier Management organizations to ensure that problems were examined throughout the value stream, and final corrective action, as well as containment strategies, were vetted by all stakeholders and undertaken as a full team initiative.

 